Which Company are you working for?Built Electrical
Which Trade are you working for?Electrical
StateWA
Date of Visit24/10/2018
Technician's NameAdam Hoes
Built Job Number34487
Swarovski in WAperth
Test Period9 Monthly
General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.auYes
If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
Are there any Warranty items needing to be repaired?No
Paint & surfaces are clean?Yes
Fixture draws able to open and close freely?Yes
Locks work on all fixtures?No
Comments

TALL DISPLAY MISSING REAR LOCK NUT

Is there chips, dents or defects to joinery?Yes
Comments

WATCH VIRTRINE GLASS NEEDS SECURING

Is there damage to skirtings?No
General cleanliness of fixtures, ceilings, P.O.S - provide detailsYes
Any issues found onsite please take photos and upload here
  • Any issues found onsite please take photos and upload here
  • Any issues found onsite please take photos and upload here
Roller shutters in working order and clean?No
Comments

N/A

General cleanliness of Façade? - provide detailsYes
Lighting operational, (eg logo)?Yes
Windows clean?Yes
Door handles clean and tight?Yes
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
Switchboard Store room 1 Non accessible not to code, too high and not 600mm clearance from door N N N 25/10/18 - John Cowles has approved works. To be completed under Job #35092
Test and tagging Entire store Multiple Nothing tagged N N N 25/10/18 - John Cowles has approved works. To be completed under Job #35092
5 rail schott spot rail Shop floor 1 Lamp fault N Y TBA John, please confirm if repairs are required
General Works Checklist
  • Inspect storefront, façade and store LED logo for correct operations and visible damage
Are there any repairs and additional works required?Yes
Fire Extinguisher Details
Type (ABE Powder) Size (4.5kg) Last Test Date Manufacture Date Pressure Indicator (Green Zone) Location In Store Compliant (Y/N)
ABE 2.5kg June/2018 09/2016 Green BOH Y
Next Test Due in 3 months24/01/2019
Site Status SelectorStore now fully compliant
Technician's NameAdam Hoes
Store Manager's NameLIANNA RITCHIE