Which Company are you working for?Built Electrical
Which Trade are you working for?Electrical
StateACT
Date of Visit18/02/2019
Technician's NameJohn Tome
Built Job Number36488
Swarovski Site in ACTcanberra
Test Period12 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
RCD Details (12 Month)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
MB 1 Y 15.3 28.3 P
MB 2 Y 15.8 28.9 P
MB 3 Y 16.8 27.4 P
MB 4 Y 17.2 26.8 P
MB 5 Y 18.3 25.6 P
MB 6 Y 17.6 28.6 P
MB 7 Y 15.4 28.9 P
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 or 120 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicatior functions correctly
  • Report any failures and provide costing to rectify (where applicable)
Is there an Emergency Light Test Facility & is it labelled properly?Yes
Timers
  • Check timers for correct operation and timing
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
MB 1 R Y Y Y P
MB 2 R N N N F Not lasting 90minutes Y N
MB 3 R Y Y Y P
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
MB 1 Y Y Y P
MB 2 Y Y Y P
General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.auYes
If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
Window Display Boxes - Is the Cabling in good conditions?Yes
Are there any Warranty items needing to be repaired?Yes
Paint & surfaces are clean?Yes
Fixture draws able to open and close freely?Yes
Locks work on all fixtures?Yes
Is there chips, dents or defects to joinery?No
Is there damage to skirtings?No
General cleanliness of fixtures, ceilings, P.O.S - provide detailsGood
Roller shutters in working order and clean?Yes
General cleanliness of Façade? - provide detailsGood
Lighting operational, (eg logo)?Yes
Windows clean?Yes
Door handles clean and tight?Yes
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
Emergency light 2 1 Failed 90 mins test Y N N
General Works Checklist
  • Inspect all furniture and fittings for visible damage
  • Inspect all walls, ceilings, skirtings and floors for visible damage
  • Inspect storefront, façade and store LED logo for correct operations and visible damage
  • Inspect roller shutter and doors for correct operations and visible damage
  • Check fire extinguishers, update compliance tags/labels
Are there any repairs and additional works required?No
Fire Extinguisher Details
Type (ABE Powder) Size (4.5kg) Last Test Date Manufacture Date Pressure Indicator (Green Zone) Location In Store Compliant (Y/N)
ABE 4.5 Feb 19 Jan 17 GREEN Storeroom Y
Next Test Due in 3 months13/05/2019
Site Status SelectorStore now fully compliant
Technician's NameJohn Tome
Store Manager's NameNadia m