Check there has been no power interruption for at least 16 hours prior to test
Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 or 120 minutes)
Re-instate power to luminaries and check that the battery charge operation indicatior functions correctly
Report any failures and provide costing to rectify (where applicable)
Is there an Emergency Light Test Facility & is it labelled properly?
Yes
Timers
Check timers for correct operation and timing
EMERGENCY LIGHTS
Distribution Board No.
ID No.
Surface mounted or recessed? (SorR)
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
Db 01
Em 02
R
Y
Y
Y
P
Db 01
Em 04
R
Y
Y
Y
P
EXIT LIGHTS
Distribution Board No.
ID No.
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
Db 01
Ex 01
Y
Y
Y
P
Db 01
Ex 02
Y
Y
Y
P
General Checklist
Check correct operation of all luminaries
Report on any faulty luminaries/control gear
Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.au
Yes
If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)
Switched Socket Outlets
Carry out visual check on SSOs for signs of misuse, blackening or deterioration
Check and report any outlets with multiple power boards overloading
Ensure any power boards used have an integral over-current limiter
Window Display Boxes - Is the Cabling in good conditions?
Yes
Are there any Warranty items needing to be repaired?
No
Paint & surfaces are clean?
Yes
Fixture draws able to open and close freely?
Yes
Locks work on all fixtures?
No
Comments
STORE ROOM DOOR STILL HAVING ISSUES. DOOR FRAME IS DAMAGED AND DOOR NEEDS TO BE REPLACED.
Is there chips, dents or defects to joinery?
Yes
Comments
CHIPS, CABINETS NEED TO BE BETTER SECURED AS COMING OFF THE WALL AND COMING APART.
Is there damage to skirtings?
No
General cleanliness of fixtures, ceilings, P.O.S - provide details
Good
Any issues found onsite please take photos and upload here
Roller shutters in working order and clean?
Yes
General cleanliness of Façade? - provide details
Good
Lighting operational, (eg logo)?
Yes
Windows clean?
Yes
Door handles clean and tight?
Yes
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item
Location of Item (on premises)
Quantity
Details of fault /problem
Repaired on Site? (YorN)
Quote to be sent? (YorN)
To return to Site
Comments
SWITCHBOARD LOCATION
BOH
X1
NOT COMPLIANT
N
Y
TBA
OH&S
Are there any repairs and additional works required?
Yes
General List of Repairs and additional works required
Defect Item
Location of Item
Details of Problem
Repaired on Site
Quote to be Sent
Comments
BACK DOOR
STORE
DOOR BROKEN/FRAME DAMAGED
N
N
JOB #50560 IN PROGRESS. SERVICE CHANNEL TRACKING #143480797
CABINETS/ BACKING WALL
STORE WIDE
NOT SECURED
N
N
24/07/20 - AS ADVISED VIA EMAIL FROM JOHN COWLES, THERE IS AN ISSUE WITH THE FLOORING CAUSING THIS. A BUILDER HAS ALREADY LOOKED INTO THIS AND IT IS A BIG JOB.
Fire Extinguisher Details
Type (ABE Powder)
Size (4.5kg)
Last Test Date
Manufacture Date
Pressure Indicator (Green Zone)
Location In Store
Compliant (Y/N)
ABE
1KG
JULY/2020
01/2018
GREEN
BOH
Y
BLANKET
1MX1M
JULY/2020
N/A
GOOD
BOH
Y
Next Test Due in 3 months
23/01/2021
Site Status Selector
Store now fully compliant
Technician's Name
ADAM HOES
Store Manager's Name
ANGELA MARSHALL