Which Company are you working for?Built Electrical
Which Trade are you working for?Electrical
StateWA
Date of Visit06/06/2017
Technician's NameAdam Hoes
Built Job Number23823 swarovski booragoon
Swarovski in WAbooragoon
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
RCD Details (6 Month)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
db 01 1 spare spare spare spare
3 spare spare spare spare
5 spare spare spare spare
7 spare spare spare spare
9 y p n/a emergency controls
11 y p n/a BOH lights
13 y p n/a L1 floor lights
15 y p n/a L2 floor lights
17 y p n/a kitchen power
19 not rcd protected not rcd protected n/a a/c
21 blank blank blank blank
23 blank blank blank blank
2 y p n/a spare
4 y p n/a spare
6 y p n/a spare
8 y p n/a spare
10 y p n/a light/timed controlled
12 y p n/a display/signage lights
14 y p n/a display cabnets
16 y p n/a comms rack power
18 y p n/a register power
20 blank blank blank blank
22 blank blank blank blank
24 blank blank blank blank
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 or 120 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicatior functions correctly
  • Report any failures and provide costing to rectify (where applicable)
Timers
  • Check timers for correct operation and timing
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
db 02 02 recessed y y y p n/a n/a n
03 recessed y y y p n/ n/a n
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
db 01 01 y y y p n/a y n
General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.auNo
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
Are there any Warranty items needing to be repaired?No
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
N/A N/A N/A N/A N/A N/A N/A N/A
General Works Checklist
  • Inspect all furniture and fittings for visible damage
  • Inspect all walls, ceilings, skirtings and floors for visible damage
  • Inspect storefront, façade and store LED logo for correct operations and visible damage
  • Inspect roller shutter and doors for correct operations and visible damage
  • Check fire extinguishers, update compliance tags/labels
Are there any repairs and additional works required?Yes
General List of Repairs and additional works required
Defect Item Location of Item Details of Problem Repaired on Site Quote to be Sent Comments
glass display cabinet front shop RGB colour changing device n n John please confirm if repairs are required
draws under watch display watches locking system n n John please confirm if repairs are required
Next Test Due in 3 months06/09/2017
Site Status SelectorStore now fully compliant
Technician's Nameadam hoes
Store Manager's Namestanis Miskovich