Which Company are you working for?Built Electrical
Which Trade are you working for?Electrical
StateVIC
Date of Visit14/06/2017
Technician's NameJoe Chetcuti
Built Job Number23795
Swarovski Site in VICknox_city
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 or 120 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicatior functions correctly
  • Report any failures and provide costing to rectify (where applicable)
Timers
  • Check timers for correct operation and timing
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB1 1 r n n y f did not illuminate on test n n
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB1 1 n n y f does not pass test n n
General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.auYes
If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
Are there any Warranty items needing to be repaired?No
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
switchboard missing infill BOH 1 exposure to live parts y n n
emergancy light near registers 1 failed test y n n
emergancy exit front of store 1 failed test y n n
36w Flurocent globes BOH 2 one working, other about to go y n n
swarovski entrance sign front of store 1 not working n y n Investigated before trading hours. Quote to be sent for repairs
General Works Checklist
  • Inspect all furniture and fittings for visible damage
  • Inspect all walls, ceilings, skirtings and floors for visible damage
  • Inspect storefront, façade and store LED logo for correct operations and visible damage
  • Inspect roller shutter and doors for correct operations and visible damage
  • Check fire extinguishers, update compliance tags/labels
Are there any repairs and additional works required?No
General List of Repairs and additional works required
Defect Item Location of Item Details of Problem Repaired on Site Quote to be Sent Comments
optical fibre projectors x 3 cases have been removed from previous electricians n n John please confirm if repairs are required once the de-fit at Essendon is completed
optical fibre projector faulty x 1 2nd case from front RHS lights not working n n John please confirm if repairs are requiredJohn please confirm if repairs are required once the de-fit at Essendon is completed
optical fibre case under registers registers gets metal frame hot so staff have turned off n n John please confirm if repairs are required once the de-fit at Essendon is completed
Next Test Due in 3 months14/09/2017
Site Status SelectorStore now fully compliant
Technician's NameJoe Chetcuti
Store Manager's Namejenny noone