Which Company are you working for?Built Electrical
Which Trade are you working for?Electrical
StateNSW
Date of Visit16/06/2017
Technician's NameRaphael Melas
Built Job Number23785
Swarovski Site in NSWcastle_hill
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
RCD Details (6 Month)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
Db1 1 Y P N N
Db1 2 Y P N N
Db1 3 Y P N N
Db1 4 Y P N N
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 or 120 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicatior functions correctly
  • Report any failures and provide costing to rectify (where applicable)
Timers
  • Check timers for correct operation and timing
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
Db1 2729 R Y Y Y P Na Na Na
Db1 2780 R Y Y Y P Na Na Na
Db1 2781 R Y Y Y P Na Na Na
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
Db1 7278 Y Y Y P Na Na Na
General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
Are there accurate switchboard legends within each switchboard? Please take a photo send with report to epm@builtelectrical.com.auYes
If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)If Yes, please upload all copies of legends here... (Limit of 6 megabytes total)
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
Are there any Warranty items needing to be repaired?No
ELECTRICAL LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
Show cases Wall bays 7 shelf show case displays LED's have discoloured N N N Can not get a part number as lights are part of the cabinet, they are little tiny canister LED fittings that are different colours. John, please confirm if repairs are required
Down lights in ceiling Ceiling 5 Covers have fallen off face of fitting N Y Y -
Switchboard BOH cupboard 1 Pole filler N N N Need to install pole filler on switchboard, quick lag board. This is a different type of pole filler and is only 15mm wide. Can't stick finger in it (therefore not dangerous) and currently has tape over it
General Works Checklist
  • Inspect all furniture and fittings for visible damage
  • Inspect storefront, façade and store LED logo for correct operations and visible damage
  • Check fire extinguishers, update compliance tags/labels
Are there any repairs and additional works required?Yes
General List of Repairs and additional works required
Defect Item Location of Item Details of Problem Repaired on Site Quote to be Sent Comments
Fire extinguiser (Flame stop, Powder Type, 2kg) BOH Out of date N N Expiry date is 05/2010. John, please confirm if replacement is required
Next Test Due in 3 months16/09/2017
Site Status SelectorStore now fully compliant
Technician's NameRapheal Melas
Store Manager's NameLana Hume