Partner NameTransit Electrical Pty Ltd
StateWA
Date of Visit15/10/2020
Technician's NameAdam Hoes
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number51798
EmailEmail hidden; Javascript is required.
The Good Guys Site in WArockingham

Location NameROCKINGHAM
HTML Block
Test PeriodBiennial Test (once every two years)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Biennial)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
POWER CHASSIE 1 Y 061 031 P
POWER CHASSIE 1 Y FAIL FAIL F FAILED TEST N
POWER CHASSIE 3 Y 029 032 P
POWER CHASSIE 3 Y 039 038 P
POWER CHASSIE 3 Y 056 060 P
POWER CHASSIE 5 Y 047 042 P
POWER CHASSIE 5 Y 050 050 P
POWER CHASSIE 5 Y 022 022 P
POWER CHASSIE 7 Y 025 034 P
POWER CHASSIE 7 Y FAIL FAIL F FAILED TEST N
POWER CHASSIE 7 Y FAIL FAIL F FAILED TEST N
POWER CHASSIE 9 Y 039 039 P
POWER CHASSIE 9 Y 044 079 P
POWER CHASSIE 9 Y FAIL FAIL F FAILED TEST N
POWER CHASSIE 11 Y SPARE SPARE P
POWER CHASSIE 11 Y 053 053 P
POWER CHASSIE 13-15 RWB Y 021 021 P
POWER CHASSIE 19-21 RWB Y 020 020 P
POWER CHASSIE 2 Y 030 030 P
POWER CHASSIE 2 Y 071 053 P
POWER CHASSIE 2 Y 039 039 P
POWER CHASSIE 4 Y 039 040 P
POWER CHASSIE 4 Y 050 051 P
POWER CHASSIE 4 Y FAIL FAIL F FAILED TEST N
POWER CHASSIE 6 Y 035 034 P
POWER CHASSIE 6 Y 029 039 P
POWER CHASSIE 8 Y 049 050 P
POWER CHASSIE 8 Y 043 046 P
POWER CHASSIE 8 Y 047 047 P
POWER CHASSIE 8 Y SPARE SPARE P
POWER CHASSIE 10 Y SPARE SPARE P
POWER CHASSIE 10 Y 045 045 P
POWER CHASSIE 10 Y 046 049 P
POWER CHASSIE 12 Y 048 049 P
POWER CHASSIE 16-18 RWB Y 019 019 P
POWER CHASSIE 22-24 RWB Y 031 021 P
THE GOOD GUYS CHASSIE 1 Y 040 040 P
THE GOOD GUYS CHASSIE 3 Y 039 039 P
THE GOOD GUYS CHASSIE 3 Y 077 076 P
THE GOOD GUYS CHASSIE 3 Y 047 047 P
THE GOOD GUYS CHASSIE 5 Y 044 043 P
THE GOOD GUYS CHASSIE 5 Y 051 051 P
THE GOOD GUYS CHASSIE 7 Y 058 059 P
THE GOOD GUYS CHASSIE 7 Y 039 048 P
THE GOOD GUYS CHASSIE 9 Y 042 048 P
THE GOOD GUYS CHASSIE 9 Y 030 032 P
THE GOOD GUYS CHASSIE 2 Y 030 029 P
THE GOOD GUYS CHASSIE 2 Y 039 039 P
THE GOOD GUYS CHASSIE 2 Y 078 078 P
THE GOOD GUYS CHASSIE 4 Y 082 085 P
THE GOOD GUYS CHASSIE 4 Y 089 087 P
THE GOOD GUYS CHASSIE 4 Y FAIL FAIL F FAILED TEST N
THE GOOD GUYS CHASSIE 6 Y 078 047 P
THE GOOD GUYS CHASSIE 6 Y 039 039 P
THE GOOD GUYS CHASSIE 6 Y 048 049 P
DB 01 1 Y FAILED FAILED F FAILED TEST N
DB 01 1 Y FAILED FAILED F FAILED TEST N
DB 01 1 Y FAILED FAILED F FAILED TEST N
DB 01 3 Y FAILED FAILED F FAILED TEST N
DB 01 3 Y FAILED FAILED F FAILED TEST N
DB 01 3 Y FAILED FAILED F FAILED TEST N
DB 01 5 Y FAILED FAILED F FAILED TEST N
DB 01 5 Y FAILED FAILED F FAILED TEST N
DB 01 5 Y FAILED FAILED F FAILED TEST N
DB 01 7 Y FAILED FAILED F FAILED TEST N
DB 01 7 Y 024 018 P
DB 01 7 Y FAILED FAILED F FAILED TEST N
DB 01 9 Y 027 021 P
DB 01 9 Y 031 022 P
DB 01 9 Y 024 016 P
DB 01 2 Y FAILED FAILED F FAILED TEST N
DB 01 2 Y 028 018 P
DB 01 2 Y FAILED FAILED F FAILED TEST N
DB 01 4 Y FAILED FAILED F FAILED TEST N
DB 01 4 Y FAILED FAILED F FAILED TEST N
DB 01 4 Y FAILED FAILED F FAILED TEST N
DB 01 6 Y FAILED FAILED F FAILED TEST N
DB 01 6 Y FAILED FAILED F FAILED TEST N
DB 01 6 Y FAILED FAILED F FAILED TEST N
DB 01 8 Y 017 008 P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB 02- lighting chassie 8 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 9 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassieng chassie 10 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 11 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 12 S 1 by 36w defused emergency batten Y N Y F BATTERY Y N
DB 02- lighting chassie 13 S 1 by 36w defused emergency batten Y N Y F BATTERY Y N
DB 02- lighting chassie 14 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 15 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 16 R Y Y Y P
DB 02- lighting chassie 17 R Y Y Y P
DB 02- lighting chassie 19 R Y Y Y P
DB 02- lighting chassie 20 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 21 S 1 by 36w defused emergency batten Y Y Y P
DB 02- lighting chassie 24 R Y Y Y P
DB 02- lighting chassie 26 R Y Y Y P
DB 02- lighting chassie 27 R Y Y Y P
DB 02- lighting chassie 28 R Y Y Y P
DB 02- lighting chassie 29 R Y Y Y P
DB 02- lighting chassie 30 R Y N Y F BATTERY Y N
DB 02- lighting chassie 31 R Y N Y F BATTERY Y N
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB 02- lighting chassie 1 Y Y Y P
DB 02- lighting chassie 2 Y Y Y P
DB 02- lighting chassie 3 Y Y Y P
DB 02- lighting chassie 4 Y Y Y P
DB 02- lighting chassie 5 Y Y Y P
DB 02- lighting chassie 6 Y Y Y P
DB 02- lighting chassie 7 Y Y Y P
DB 02- lighting chassie 18 Y Y Y P
DB 02- lighting chassie 22 Y Y Y P
DB 02- lighting chassie 23 Y Y Y P
DB 02- lighting chassie 25 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
2 x 36w defused battens Y
1 by 36w defused batten Y
4 foot LED slimline batten Y
400w mh hibay Y
LED hibay Y
Exit sign Y
2 by 36w emergency batten Y
1 by 36w emergency batten Y
50w hallogen down light Y
Emergency spit fire Y
Oyster light Y
2 by 28w wp battens Y
LED flood light Y
2 by 36w troffer lights Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
RCBO POWER CHASSIE B1,W7,B7,B9,B4 FAILED TEST TRIP TIME AND PUSH N N Y 22/10/20 - QUOTE #2533 APPROVED BY HEAD OFFICE. WORKS IN PROGRESS
RCBO DB 01 R1,W1,B1,R3,W3,B3,R5,W5,B5,R7,B7,W7, R2,W2,R4,W4,B4,R6,W6,B6 FAILED TEST N N Y 22/10/20 - QUOTE #2533 APPROVED BY HEAD OFFICE. WORKS IN PROGRESS
PELMET LIGHTS AUDIO SYSTEMS X1 NOT ILLUMINATED, REQUIRE 8 X LED LINKABLES N Y TBA
PELMET LIGHTS ACCESSORIES X1 NOT ILLUMINATED, REQUIRE 8 X LED LINKABLES N Y TBA
PELMET LIGHTS WALL MOUNTS X1 NOT ILLUMINATED, REQUIRE 8 X LED LINKABLES N Y TBA
SURFACED MOUNT EMERGENCY EM 11 AND 12 X2 FAILED TEST Y N N OH&S
RECESSED EM EM 30 AND 31 X2 FAILED TEST Y N N OH&S
FISHER AND PAYKEL DISPLAY POWER ISSUE X1 LEADS UNPLUGGED Y N N POWER
Site Status SelectorCompleted but with repairs required
Next Test Due in 6 months15/04/2021