StateVIC
Date of Visit26/10/2020
Technician's NameNathan McBain
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number51746
EmailEmail hidden; Javascript is required.
The Good Guys Site in VICnarre_warren

Location NameNarre Warren
HTML Block
Test PeriodBiennial Test (once every two years)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Biennial)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB-13 13 Y 27 21 P
DB-13 15 Y 27 22 P
DB-13 17 Y 28 21 P
DB-13 21 Y 27 21 P
DB-13 23 Y 28 23 P
DB-13 30 Y 28 22 P
DB-13 34 Y 27 22 P
DB-13 35 Y 27 22 P
DB-13 42 Y 27 20 P
DB-13 44 Y 29 21 P
DB-13 45 Y 32 32 P
DB-13 46 Y 37 38 P
DB-13 47 Y 33 34 P
DB-13 48 Y 47 21 P
DB-13A 01 Y 19 19 P
DB-13A 02 Y 19 19 P
DB-13A 03 Y 19 19 P
DB-13A 04 Y 21 22 P
DB-13A 05 Y 21 21 P
DB-13A 06 Y 18 19 P
DB-13A 07 Y 18 19 P
DB-13A 08 Y 19 18 P
DB-13A 10 Y 29 18 P
DB-13A 12 Y 19 19 P
DB-13A 13 Y 19 19 P
DB-13A 15 Y 20 18 P
DB-13A 17 Y 19 19 P
DB-13A 19 Y 20 20 P
DB-13A 21 Y 19 19 P
DB-13A 23 Y 20 19 P
DB-13A 25 Y 28 30 P
DB-13A 26 Y 19 19 P
DB-13A 28 Y 19 19 P
DB-13A 30 Y 19 19 P
DB-13A 32 Y 19 19 P
DB-12 06 Y 36 22 P
DB-12 18 Y 28 21 P
DB-12 21 Y 28 22 P
DB-12 22 Y 27 21 P
DB-12 23 Y 27 20 P
DB-12 27 Y 27 21 P
DB-12 28 Y 28 22 P
DB-12 29 Y 27 21 P
DB-12 30 Y 27 21 P
DB-12 33 Y 27 20 P
DB-12 34 Y 27 21 P
DB-12 35 Y 27 19 P
DB-12 36 Y 27 21 P
DB-12 38 Y 28 21 P
DB-12 47 Y 27 21 P
DB-12 48 Y 27 21 P
DB-12B 01 Y 42 32 P
DB-12B 02 Y 42 32 P
DB-12B 03 Y 42 36 P
DB-12B 04 Y 154 34 P
DB-12B 05 Y 73 33 P
DB-12B 06 Y 107 33 P
DB-12B 07 Y 28 34 P
DB-12B 08 Y 42 32 P
DB-12B 09 Y 42 32 P
DB-12B 10 Y 42 36 P
DB-12B 11 Y 42 32 P
DB-12B 12 Y 34 36 P
DB-12B 13 Y 30 32 P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-12 2 S Y Y Y P
DB-12 3 S Y Y Y P
DB-12 5 S Y Y Y P
DB-12 6 S Y Y Y P
DB-12 7 R Y Y Y P
DB-12 9 R Y Y Y P
DB-13 11 S Y Y Y P
DB-13 12 S Y Y Y P
DB-13 14 S Y N Y F FAILED BATTERY TEST Y N
DB-13 15 S Y N Y F FAILED BATTERY TEST Y N
DB-13 18 R Y Y Y P
DB-13 19 R Y Y Y P
DB-13 20 R Y Y Y P
DB-13 21 R Y Y Y P
DB-13 22 R Y Y Y P
DB-13 23 R Y Y Y P
DB-13 24 R Y Y Y P
DB-13 25 R Y Y Y P
DB-13 26 S Y Y Y P
DB-13 28 R Y Y Y P
DB-13 30 S Y Y Y P
DB-13 31 S Y Y Y P
DB-13 32 S Y N Y F FAILED BATTERY TEST Y N
DB-13 33 S Y N Y F FAILED BATTERY TEST Y N
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-12 1 Y Y Y P
DB-12 4 Y Y Y P
DB-12 8 Y Y Y P
DB-13 10 Y Y Y P
DB-13 13 Y Y Y P
DB-13 16 Y Y Y P
DB-13 17 Y Y Y P
DB-13 27 Y Y Y P
DB-13 29 Y Y Y P
DB-13 34 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
HI-BAY LIGHTS Y
SINGLE DIFFUSED T5 Y
DOUBLE BEAR TWIN BATTEN T5 Y
LED DOWNLIGHT Y
2FT SQUARE DIFFUSED Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
EM32 BOH AISLE HALF WAY DOWN 1 FAILED BATTERY TEST Y N N REPLACE WITH DUEL LED SURFACE MOUNT. SCISSOR LIFT REQUIRED 7.3M TO FITTING
EM33 BOH AISLE NEAR SINGL MAN EXIT DOOR 1 FAILED BATTERY TEST Y N N REPLACE WITH DUEL LED SURFACE MOUNT. SCISSOR LIFT REQUIRED 7.3M TO FITTING
EM15 FRIDGES 1 FAILED BATTERY TEST Y N N REPLACE WITH DUEL LED SURFACE MOUNT. SCISSOR LIFT REQUIRED 7.3M TO FITTING
EM14 FRIDGES 1 FAILED BATTERY TEST Y N N REPLACE WITH DUEL LED SURFACE MOUNT. SCISSOR LIFT REQUIRED 7.3M TO FITTING
DAVIS LED BATTEN OFFICE FRONT 1 FITTING FAILED TO ILLUMINATE Y N N REPLACED WITH NEW 35W DAVIS LED BATTEN
SQUARE LED PANEL LIGHT WASHING MACHINES ON BULKHEAD 1 FITTING FAILED TO ILLUMIMATE N Y TBC QUOTE TO BE SENT FOR APPROVAL. SCISSOR REQUIRED FOR HIGH ACCESS.
SQUARE LED PANEL LIGHT STEAMERS BULKHEAD 1 FITTING FAILED TO ILLUMINATE N Y TBC QUOTE TO BE SENT FOR APPROVAL. SCISSOR REQUIRED FOR HIGH ACCESS.
RACK LIGHT BOX FRIDGES 1 LIGHT BOX FAILED TO ILLUMINATE N Y TBC QUOTE TO BE SENT FOR APPROVAL
DB-12 TV AREA 1 CB21 TRIPPING N Y TBC OLD LIGHTS CAUSING CB TO TRIP. QUOTE TO BE SUBMITTED FOR APPROVAL
Site Status SelectorStore now fully compliant
Next Test Due in 6 months26/04/2021