Date of Visit13/10/2020
Technician's NameDan
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number51796
EmailEmail hidden; Javascript is required.
The Good Guys Site in WAmalaga

Location NameMalaga
HTML Block
Test PeriodBiennial Test (once every two years)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Biennial)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB1 W3 Y 28 19 P
B3 Y 19 27 P
W9 Y 28 45 P
11R Y 28 10 P
11W Y 45 - F Not tripping at 180 degrees Y
11B Y - - F Not tripping at 0 or 180 degrees Y
13R Y 27 27 P
13W Y 33 11 P
15R Y 28 28 P
15W Y 484 48 P
23R Y 29.9 29 P
23W Y 29 29 P
27R Y 27 27 P
31R Y 110 110 P
31B Y 28 18 P
33R Y 28 19 P
33W Y 28 20 P
33B Y 38 28 P
10R Y 66 25 P
10W Y 18 23 P
10B Y 37 37 P
12R Y 28 28 P
12W Y 27 28 P
12B Y 30 29 P
32R Y 28 19 P
32B Y 28 19 P
34R Y 28 19 P
34W Y 28 19 P
W32 Y 27 16 P
R7 Y 28 19 P
R9 Y 22 16 P
B6 Y 18 28 P
B8 Y 28 18 P
R19 Y 28 19 P
W19 Y 28 19 P
R27 Y 32 32 P
W20 Y 30 30 P
B20 Y 30 30 P
W24 Y 44 44 P
B24 Y 18 18 P
R28 Y 100 96 P
W28 Y 26 26 P
B28 Y 42 42 P
R30 Y 29 29 P
B30 Y 23 19 P
DB2 5R Y 29 29 P
5W Y 36 36 P
5B Y 35 7 P
7R Y 28 31 P
7W Y 36 35 P
7B Y 26 29 P
9R Y 29 52 P
9W Y 28 45 P
9B Y 43 43 P
6R Y 28 28 P
6W Y 28 33 P
6B Y 44 35 P
8R Y 28 28 P
8W Y 36 30 P
8B Y 30 29 P
10R Y 31 31 P
18W Y 28 19 P
1R Y 30 29 P
1B Y 65 52 P
3R Y 30 30 P
2R Y 29 29 P
2W Y 29 29 P
W3 Y 27 28 P
B3 Y 28 19 P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB 01 2 R Y Y Y P
DB 01 3 Twin tubed batten Y Y Y P
DB 01 4 Twin tubed batten Y Y Y P
DB 01 5 Twin tubed batten Y Y Y P
DB 01 6 Twin tubed batten Y Y Y P
DB 01 7 Twin tubed batten Y Y Y P
DB 01 8 Twin tubed batten Y Y Y P
DB 01 9 Twin tubed batten Y Y Y P
DB 01 10 Twin tubed batten Y Y Y P
DB 01 11 Twin tubed batten Y Y Y P
DB 01 12 Twin tubed batten Y Y Y P
DB 02 13 R Y Y Y P
DB 02 14 R Y Y Y P
DB 02 15 R Y Y Y P
DB 02 17 R Y Y Y P
DB 02 19 R Y Y Y P
DB 02 20 R Y Y Y P
DB 02 22 Twin tubed batten Y Y Y P
DB 02 23 Twin tubed batten Y Y Y P
DB 02 24 Twin tubed batten Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB 01 1 Y Y Y P
DB 01 16 Y Y Y P
DB 02 18 Y Y Y P
DB 02 21 Y Y Y P
DB 02 22 Y Y Y P
DB 02 26 Y Y Y P
DB 01 27 Y Y Y P
DB 01 28 Y Y Y P
DB 01 29 Y Y Y P
DB 01 30 Y Y Y P
DB 01 31 Y Y Y P
DB 01 32 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
400w low bay Y
400w low bay defused Y
1 by 36w defused battens Y
40w oyster light Y
50w 12v down lights Y
150w mh shop lights Y
400w hibay Y
Exit Y
Emergency spit fire em Y
Emergency 2 by 36w Y
40w b27 batten globe Y
LED spot lights Y
60w bunker lights Y
Par 38 twin spots Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
DB 01 - 11W & 11B SWITCHBOARD 2 FAULTY Y N N
Site Status SelectorStore now fully compliant
Next Test Due in 6 months13/04/2021