Partner NameSturdie Trade Services
StateVIC
Date of Visit01/10/2021
Technician's NameNathan McBain
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number57717
EmailEmail hidden; Javascript is required.
The Good Guys Site in VICessendon

Location NameESSENDON
HTML Block
Test Period12 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Initial/12 Months)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB1-2 01 Y P
DB1-2 02 Y P
DB1-2 03 Y P
DB1-2 04 Y P
DB1-2 05 Y P
DB1-2 06 Y P
DB1-2 07 Y P
DB1-2 08 Y P
DB1-2 09 Y P
DB1-2 10 Y P
DB1-2 11 Y P
DB1-2 12 Y P
DB1-2 13 Y P
DB1-2 14 Y P
DB1-2 17 Y P
DB1-2 18 Y P
DB1-2 22 Y P
DB1-2 23 Y P
DB1-2 24 Y P
DB1-2 25 Y P
DB1-2 27 Y P
DB1-2 29 Y P
DB1-2 31 Y P
DB1-2 32 Y P
DB1-2 34 Y P
DB1-2 36 Y P
DB1-2 38 Y P
DB1-2 40 Y P
DB T - 01 02 Y P
DB T - 01 04 Y P
DB T - 01 06 Y P
DB T - 01 08 Y P
DB T - 01 10 Y P
DB T - 01 12 Y P
DB T - 01 14 Y P
DB T - 01 16 Y P
DB T - 01 18 Y P
DB T - 01 20 Y P
DB T - 01 22 Y P
DB T - 01 24 Y P
DB T - 01 26 Y P
DB T - 01 28 Y P
DB T - 01 30 Y P
DB T - 01 32 Y P
DB T - 01 34 Y P
DB T - 01 36 Y P
DB T - 01 38 Y P
DB T - 01 40 Y P
DB T - 01 42 Y P
DB T - 01 44 Y P
DB T - 01 46 Y P
DB T - 01 48 Y P
DB T - 01 50 Y P
DB T - 01 83 Y P
DB T - 01 84 Y P
DB1 - 1 01 Y P
DB1 - 1 02 Y P
DB1 - 1 03 Y P
DB1 - 1 04 Y P
DB1 - 1 05 Y P
DB1 - 1 09 Y P
DB1 - 1 10 Y P
DB1 - 1 11 Y P
DB1 - 1 13 Y P
DB1 - 1 14 Y P
DB1 - 1 15 Y P
DB1 - 1 16 Y P
DB1 - 1 17 Y P
DB1 - 1 18 Y P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
  • Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-1/1 1 S Y Y Y P
DB-1/1 2 S Y Y Y P
DB-1/1 3 S Y Y Y P
DB-1/1 4 S Y Y Y P
DB-1/1 5 S Y Y Y P
DB-1/1 6 S Y Y Y P
DB-1/1 7 S Y Y Y P
DB-1/1 8 S Y Y Y P
DB-1/1 9 S Y Y Y P
DB-1/1 10 S Y Y Y P
DB-1/1 11 S Y Y Y P
DB-1/1 12 S Y Y Y P
DB-1/1 13 S Y Y Y P
DB-1/1 14 S Y Y Y P
DB-1/1 15 S Y Y Y P
DB-1/1 16 S Y Y Y P
DB-1/1 17 R Y Y Y P
DB-1/1 18 R Y Y Y P
DB-1/1 19 R Y Y Y P
DB-1/1 20 R Y Y Y P
DB-1/1 21 R Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-1/1 1 Y Y Y P
DB-1/1 2 Y N Y F FAILED BATTERY TEST Y N
DB-1/1 3 Y Y Y P
DB-1/1 4 Y Y Y P
DB-1/1 5 Y Y Y P
DB-1/1 6 Y Y Y P
DB-1/1 7 Y Y Y P
DB-1/1 8 Y Y Y P
DB-1/1 9 Y Y Y P
DB-1/1 10 Y Y Y P
DB-1/1 11 Y Y Y P
DB-1/1 12 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
High-Bay Lights Y
Square High-Bay Lights Y
LED Downlights Y
Twin Fluorescent Lights Y
Are there any Warranty items needing to be repaired?Yes
WARRANTY
Defect Item Location of Item (on premises) Quantity Details of fault/problem Manufacturer Part Number Repaired on Site Comments
DAVIS HIGHBAY BOH NEAR DB 1 FAILED TO ILLUMINATE DAVIS Y REPLACED WITH NEW
DAVIS HIGHBAY SHOP FLOOR BETWEEN TVS AND DYSON DISPLAY 1 FAILED TO ILLUMINATE DAVIS Y REPLACED WITH NEW
DAVIS HIGHBAY FRIDGES ABOVE SAT COUNTER 1 FAILED TO ILLUMINATE DAVIS Y REPLACED WITH NEW
DAVIS HIGHBAY KINSMAN DISPLAY 1 FAILED TO ILLUMINATE/DIM DAVIS Y REPLACED WITH NEW
DAVIS HIGHBAY MIELE WASHING MACHINES 1 FAILED TO ILLUMINATE/DIM DAVIS Y REPLACED WITH NEW
Geotag photo(s)
  • Have you sent the Geotag photo(s) to maintenance@sturdie.com.au, referring to the Store Location in the email, e.g. Canberra City?
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
TEST AND TAG STORE 80+ TEST AND TAG INDATE, NECT TEST DUE 13 JAN 2022 N N N OBSERVATION
KINSMAN DISPLAY LIGHTING PENDANTS 5 FAILED TO ILLUMINATE Y N N REPLACED 2 X 10W LAMPS AND 3 X 4W LAMPS
EX02 BOH 1 FAILED BATTERY TEST Y N N REPLACED WITH NEW
Site Status SelectorStore now fully compliant
Next Test Due in 6 months01/04/2022