Partner NameBuilt Electrical Australia
StateNSW
Date of Visit03/02/2022
Technician's NamePeter Hay
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number62335
EmailEmail hidden; Javascript is required.
The Good Guys Site in NSWcastle_hill

Location NameCastle Hill
HTML Block
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

RCD Details (6 Month)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB1 17 Y P
DB2 8 Y P
10 Y P
14 Y P
20 Y P
21 Y P
DB3 17 Y P
DB4 4 Y P
8 Y P
16 Y P
18 Y P
24 Y P
DB5 1 Y P
2 Y P
3 Y P
4 Y P
5 Y P
6 Y P
7 Y P
8 Y P
9 Y P
10 Y P
11 Y P
12 Y P
13 Y P
14 Y P
15 Y P
16 Y P
17 Y P
18 Y P
19 Y P
20 Y P
21 Y P
22 Y P
23 Y P
24 Y P
25 Y P
26 Y P
27 Y P
28 Y P
29 Y P
30 Y P
31 Y P
33 Y P
34 Y P
35 Y P
36 Y P
DB5 ADJ MAIN SWITCH POWER TV N32 Y P
DB5 ADJ MAIN SWITCH POWER TV N32 Y P
DB5 ADJ MAIN SWITCH POWER BAY N1 Y P
DB5 ADJ MAIN SWITCH POWER BAY N2 Y P
DB5A 1 Y P
2 Y P
3 Y P
4 Y P
5 Y P
6 Y P
7 Y P
8 Y P
9 Y P
SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
  • Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
1 R Y Y Y P
2 S Y Y Y P
3 R Y Y Y P
4 R Y Y Y P
5 R Y Y Y P
6 S Y Y Y P
7 S Y Y Y P
8 S Y Y Y P
9 S Y Y Y P
10 S Y Y Y P
11 S Y Y Y P
12 S Y Y Y P
13 S Y Y Y P
14 S Y Y Y P
15 S Y Y Y P
16 S Y Y Y P
17 S Y Y Y P
18 S Y Y Y P
19 R Y Y Y P
20 R Y Y Y P
21 R Y Y Y P
22 R Y Y Y P
23 R Y Y Y P
24 S Y Y Y P
25 R Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
1 Y Y Y P
2 Y Y Y P
3 Y Y Y P
4 Y Y Y P
5 Y Y Y P
6 Y Y Y P
7 Y Y Y P
8 Y Y Y P
9 Y Y Y P
10 Y Y Y P
11 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auNo
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
Fluoro High-bays 200W Y
LED 4ft Fluoro 20W Y
2ft Single Fluoro 840 Y
4ft Single Fluoro 840 Y
4ft Twin Fluoro 840 Y
4ft Twin LED Fluoro 18W Y
4ft Single LED Fluoro 18W Y
Shop Light Rectangle 38W Y
LED Downlight 9W Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
Schedule Db1, db2, db4 3 Missing N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
RCD Throughout Store Various Upgrade required N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Main switch handle Db2 1 Missing N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Db5 eschuloen Tv section 1 Needs to have hole covered N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Extension lead LG dishwashers 1 Tied and suspended from fire pipe. Needs a new dropper installed correctly. N N N FYI
Power dropper Bosch dishwashers 1 Missing N N N FYI
High bay Westinghouse kitchen display 1 Light level too low. 1 additional high bay needed N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Exit Light Kinsman display 1 Blocked by display. Needs to be relocated. N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Light box Simpson washing machines 1 Not illuminated N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Light boxes Solt washing machines 2 Flickering N TBA TBA Added to fortnightly repairs list, please advise if quote is required.
Power Cable BOH 1 Bare end. Coiled up on ceiling. Make safe or remove. Y N N Repaired.
Emergency Light Plan Site Folder 1 Not accurate Y N N Site audited and new plan marked up and left in site folder.
Site Status SelectorCompleted but with repairs required
Next Test Due in 6 months03/08/2022