StateNSW
Date of Visit06/07/2022
Technician's NameCon Karakiozis
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number66871
EmailEmail hidden; Javascript is required.
The Good Guys Site in NSWmarsden_park

Location NameMarsden Park
HTML Block
Test PeriodBiennial Test (once every two years)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Biennial)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DBT12A 1 Y 19 19 P
2 Y 20 20 P
3 Y 20 20 P
4 Y 19 19 P
5 Y 31 32 P
6 Y 23 30 P
7 Y 19 19 P
8 Y 19 21 P
9 Y 19 19 P
10 Y 19 19 P
11 Y 19 19 P
12 Y 17 17 P
13 Y 20 19 P
15 Y 19 19 P
17 Y 19 19 P
19 Y 19 19 P
21 Y 19 18 P
22 Y 15 15 P
23 Y 20 20 P
24 Y 19 19 P
25 Y 14 14 P
27 Y 18 19 P
29 Y 19 21 P
31 Y 20 20 P
37 Y 21 21 P
51 Y 21 20 P
53 Y 17 17 P
55 Y 20 19 P
DBT12B 1 Y 15 15 P
2 Y 20 19 P
3 Y 21 19 P
4 Y 19 19 P
5 Y 20 19 P
6 Y 22 21 P
7 Y 19 20 P
8 Y 30 29 P
9 Y 17 17 P
10 Y 22 22 P
11 Y 20 23 P
12 Y 16 16 P
13 Y 25 21 P
14 Y 19 19 P
15 Y 19 19 P
16 Y 17 17 P
17 Y 16 15 P
18 Y 19 19 P
19 Y 16 16 P
20 Y 19 19 P
21 Y 19 19 P
25 Y 19 20 P
27 Y 18 19 P
28 Y 19 20 P
29 Y 17 17 P
30 Y 19 19 P
31 Y 24 24 P
32 Y 19 19 P
33 Y 15 15 P
34 Y 14 19 P
36 Y 19 19 P
DBT12B-SUBBOARD 22 Y 18 18 P
24 Y 33 33 P
26 Y 34 34 P
44 Y 32 32 P
55 Y 19 19 P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
  • Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DBT12A EM1 S Y Y Y P
EM2 S Y Y Y P
EM3 S Y Y Y P
EM4 S Y Y Y P
EM5 S Y Y Y P
EM6 S Y Y Y P
EM7 S Y Y Y P
EM8 S Y Y Y P
EM9 R Y Y Y P
EM10 R Y Y Y P
EM11 R Y Y Y P
EM12 R Y Y Y P
EM13 R Y Y Y P
EM14 R Y Y Y P
EM15 R Y Y Y P
EM16 R Y Y Y P
EM17 R Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DBT12A EX1 Y Y Y P
EX2 Y Y Y P
EX3 Y Y Y P
EX4 Y Y Y P
EX5 Y F Y P FAULTY BATTERY Y N
EX6 Y Y Y P
EX7 Y Y Y P
EX8 Y Y Y P
EX9 Y Y Y P
EX10 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
1 KITCHENS 1 LED DOWNLIGHT NO POWER. Y N N OPENED DISPLAY AND INSTALLED A NEW POWER BOARD ABOVE RANGE HOODS TO SUPPLY DOWN LIGHT.
2 05 - BOH 1 FAULTY EXIT Y N N REPLACED FITTING
3 STAFF KITCHEN 1 FAULTY ELECTRONIC BALLAST Y N N REPLACED ELECTRONIC BALLAST AND 2 X 28W TUBES
4 TV SECTION 2 THE TCL TV RACK HAS TWO OF THE FOUR SIGNS NOT WORKING. N/A N/A N/A SUPPLIER TO ORGANISE TO REPAIR.
5 DRYER SECTION 1 FISHER AND PAYKEL SIGN NOT LIT N/A N/A N/A SUPPLIER TO SEND CONTRACTOR TO REPAIR.
6 BOH 1 DOOR BELL Y N N INSTALLED NEW WEATHER PROOF DOOR BELL.
7 STORE SWITCH BOARD SCHEDULES 1 SWITCHBOARD LEGENDS NOT CORRECT Y N N SWITCHBOARD TB12B SCHEDULE WAS NOT CORRECT. WE COMPLETED FRONT OF STORE AUDIT AND COMPLETED NEW ASBUILTS AND SWITCHBOARD LEGEND.
8 THROUGHOUT STORE 1 EMERGENCY LIGHT PLAN Y N N COMPLETED FULL STORE AUDIT ON EMERGENCY LIGHTS AND COMPLETED A NEW MARKED UP DRAWING OF ALL EMERGENCY LIGHTS. THE ORIGINAL DRAWING HAD MISSING FITTINGS.
9 FRONT MAIN COUNTER 1 THE POWER CIRCUIT THAT SUPPLIES THE MAIN COUNTER ALSO SUPPLIES LAPTOP TABLE. THIS MAY CAUSE A RISK OF THE MAIN COUNTER BEING SHUT OFF BY ACCIDENT OR BY A FAULT TO THE LAPTOP TABLE. WE WILL NEED TO INSTALL NEW POWER CIRCUIT TO LAPTOP TABLE AND JUNCTION THE MAIN COUNTER CABLE (TB12B - CB29) N N N ADDED TO FORTNIGHTLY REPAIRS LIST
10 THROUGHOUT STORE 1 THERE ARE MANY CIRCUITS THAT ARE OVER LOADED. CIRCUITS REQUIRE SPLITTING N N N ADDED TO FORTNIGHTLY REPAIRS LIST
Site Status SelectorStore now fully compliant
Next Test Due in 6 months06/01/2023