Carry out push button test and record the results below.
RCD Details (Biennial)
Distribution Board No.
Circuit No.
Push Button (YorN)
0 Degrees
180 Degrees
Pass / Fail (PorF)
Fault?
Repaired on Site (YorN)
DB T-01
2
Y
32
23
P
DB T-01
4
Y
26
18
P
DB T-01
6
Y
26
17
P
DB T-01
8
Y
30
22
P
DB T-01
10
Y
29
19
P
DB T-01
12
Y
28
18
P
DB T-01
14
Y
27
16
P
DB T-01
16
Y
133
21
P
DB T-01
18
Y
25
17
P
DB T-01
20
Y
24
16
P
DB T-01
22
Y
180
27
P
DB T-01
24
Y
25
16
P
DB T-01
26
Y
177
16
P
DB T-01
28
Y
29
18
P
DB T-01
30
Y
28
18
P
DB T-01
32
Y
28
18
P
DB T-01
34
Y
28
19
P
DB T-01
36
Y
25
16
P
DB T-01
38
Y
28
18
P
DB T-01
40
Y
28
18
P
DB T-01
42
Y
28
18
P
DB T-01
44
Y
28
18
P
DB T-01
46
Y
25
16
P
DB T-01
48
Y
28
18
P
DB T-01
50
Y
28
18
P
DB T-01
52
Y
28
18
P
DB T-01
54
Y
28
18
P
DB T-01
56
Y
28
18
P
DB T-01
58
Y
28
18
P
DB T-01
83
Y
28
18
P
DB T-01
84
Y
29
18
P
DB1-1
1
Y
28
38
P
DB1-1
2
Y
28
19
P
DB1-1
3
Y
29
38
P
DB1-1
4
Y
28
38
P
DB1-1
5
Y
28
18
P
DB1-1
9
Y
30
40
P
DB1-1
10
Y
30
40
P
DB1-1
11
Y
30
40
P
DB1-1
13
Y
28
18
P
DB1-1
14
Y
29
19
P
DB1-1
15
Y
28
38
P
DB1-1
16
Y
29
19
P
DB1-1
17
Y
25
17
P
DB1-1
18
Y
26
17
P
DB1-2
1
Y
29
39
P
DB1-2
2
Y
28
38
P
DB1-2
3
Y
29
39
P
DB1-2
4
Y
30
40
P
DB1-2
5
Y
25
40
P
DB1-2
6
Y
68
45
P
DB1-2
7
Y
32
38
P
DB1-2
8
Y
28
38
P
DB1-2
9
Y
29
31
P
DB1-2
10
Y
28
40
P
DB1-2
11
Y
35
45
P
DB1-2
12
Y
23
38
P
DB1-2
13
Y
22
30
P
DB1-2
14
Y
22
30
P
DB1-2
17
Y
27
31
P
DB1-2
18
Y
28
38
P
DB1-2
22
Y
25
17
P
DB1-2
23
Y
25
16
P
DB1-2
24
Y
25
18
P
DB1-2
25
Y
28
18
P
DB1-2
27
Y
28
18
P
DB1-2
29
Y
25
17
P
DB1-2
31
Y
27
18
P
DB1-2
32
Y
25
16
P
DB1-2
34
Y
25
20
P
DB1-2
36
Y
42
19
P
DB1-2
38
Y
25
17
P
DB1-2
40
Y
28
18
P
THERMOGRAPHIC TEST RESULTS
THERMOGRAPHIC TEST RESULTS
SF43 Exit/Emergency
SF43 EXIT/EMERGENCY LIGHTING
Exit/Emergency Light Checklist
Check there has been no power interruption for at least 16 hours prior to test
Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Exit/Emergency Light Checklist
Check there has been no power interruption for at least 16 hours prior to test
Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
Check timers for correct operation and timing
Switched Socket Outlets
Carry out visual check on SSOs for signs of misuse, blackening or deterioration
Check and report any outlets with multiple power boards overloading
Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No.
ID No.
Surface mounted or recessed? (SorR)
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
DB-1/1
1
S
Y
Y
Y
P
DB-1/1
2
S
Y
Y
Y
P
DB-1/1
3
S
Y
Y
Y
P
DB-1/1
4
S
Y
Y
Y
P
DB-1/1
5
S
Y
Y
Y
P
DB-1/1
6
S
Y
Y
Y
P
DB-1/1
7
S
Y
Y
Y
P
DB-1/1
8
S
Y
Y
Y
P
DB-1/1
9
S
Y
Y
Y
P
DB-1/1
10
S
Y
Y
Y
P
DB-1/1
11
S
Y
Y
Y
P
DB-1/1
12
S
Y
Y
Y
P
DB-1/1
13
S
Y
Y
Y
P
DB-1/1
14
S
Y
Y
Y
P
DB-1/1
15
S
Y
N
Y
F
FAILED BATTERY TEST
Y
N
DB-1/1
16
S
Y
Y
Y
P
DB-1/1
17
R
Y
Y
Y
P
DB-1/1
18
R
Y
Y
Y
P
DB-1/1
19
R
Y
Y
Y
P
DB-1/1
20
R
Y
Y
Y
P
DB-1/1
21
R
Y
Y
Y
P
HTML Block
EXIT LIGHTS
Distribution Board No.
ID No.
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
DB-1/1
1
Y
Y
Y
P
DB-1/1
2
Y
Y
Y
P
DB-1/1
3
Y
Y
Y
P
DB-1/1
4
Y
Y
Y
P
DB-1/1
5
Y
Y
Y
P
DB-1/1
6
Y
Y
Y
P
DB-1/1
7
Y
Y
Y
P
DB-1/1
8
Y
Y
Y
P
DB-1/1
9
Y
Y
Y
P
DB-1/1
10
Y
Y
Y
P
DB-1/1
11
Y
Y
Y
P
DB-1/1
12
Y
Y
Y
P
SF44 General Lighting & Works
SF44 GENERAL LIGHTING & WORKS
General Checklist
Check correct operation of all luminaries
Report on any faulty luminaries/control gear
Provide costing to repair/replace
HTML Block
General Operation/Additional items
Check with Store Manager to ensure there are no other issues
Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.au
Yes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten)
Existing (YorN)
Hi-bay lights
Y
Square Hi-bay lights
Y
LED downlights
Y
Twin fluorescent lights
Y
Are there any Warranty items needing to be repaired?
Yes
WARRANTY
Defect Item
Location of Item (on premises)
Quantity
Details of fault/problem
Manufacturer
Part Number
Repaired on Site
Comments
DAVIS HIGH BAY
FRIDGES CLOSER TO WALL LG SIGNATURE DISPLAY
1
FAILED TO ILLUMINATE
DAVIS
-
N
SCISSOR LIFT REQUIRED, 7.2M AFL.
DAVIS HIGH BAY
STEAMERS
1
FAILED TO ILLUMIMATE
DAVIS
-
N
SCISSOR LIFT REQUIRED 8.0M AFL
DAVIS HIGH BAY
FRIDGES BETWEEN 2 × LG FRIDGES END CAPS
1
INTERMITTENT FAULT ON/OFF 4 TIMES WHILE ONSITE
DAVIS
-
N
SCISSOR LIFT REQUIRED 8.0 AFL
Geotag photo(s)
Have you sent the Geotag photo(s) to maintenance@sturdie.com.au, referring to the Store Location in the email, e.g. Canberra City?
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item
Location of Item (on premises)
Quantity
Details of fault /problem
Repaired on Site? (YorN)
Quote to be sent? (YorN)
To return to Site
Comments
TEST AND TAG
STORE
80+
TEST AND TAG IN-DATE , NEXT TEST DUE 29 MARCH 2023
N
N
N
OBSERVATION
DISPLAY LIGHTING
VIALI KITCHEN WALL DISPLAY
3
FAILED TO ILLUMINATE
Y
N
N
LED GLOBE
KINSMAN
2
FAILED TO ILLUMINATE
Y
N
N
DISPLAY LIGHTING
TECHNIKA
1
FAILED TO ILLUMINATE
Y
N
N
REPLACE WITH TRI COLOUR SAL LED LINKABLE
EM15
AIRLOCK
1
FAILED BATT TEST
Y
N
N
EXTERNAL TGG ILLUMINATED SIGN/LETTERS
EXTERNAL FRONT
1
MAJORITY OF LETTERS FAILED TO ILLUMINATE
N
TBA
TBA
EWP REQUIRED TO ACCESS SIGN TO INVESTIGATE INTERNAL TO DETERMIN WHAT IS FAULTY. ALL WORK WOULD NEED TO BE DONE BEFORE TRADE DUE TO WORKING AT FRONT ENTRANCE. 9.0M TO BOTTOM OF SIGN. ADDED TO FORTNIGHTLY REPAIRS LIST.
CLIPSAL 56 SERIES EXTERNAL WEATHERPROFF 10A GPO
EXTERNAL FRONT NEAR SINGLE MAN DOOR
1
FAULTY SWITCH
Y
N
N
Site Status Selector
Store now fully compliant
Next Test Due in 6 months
05/04/2023