State | ACT |
---|
Date of Visit | 03/10/2023 |
---|
Technician's Name | Will Andrews |
---|
Which Company are you working for? | Sturdie Trade Services |
---|
Sturdie Job Number | 50F0015/0109 |
---|
Email | Email hidden; Javascript is required. |
---|
The Good Guys Site in ACT | belconnen |
---|
|
|
---|
Location Name | Belconnen |
---|
| |
---|
HTML Block |
|
---|
Test Period | 12 Monthly (90 minutes) |
---|
Push Button Test | - Carry out push button test for correct operation
|
---|
Carry out push button test for correct operation | |
---|
HTML Block |
|
---|
Carry out test with RCD Tester | Carry out push button test and record the results below. |
---|
RCD Details (Initial/12 Months) | Distribution Board No. |
Circuit No. |
Push Button (YorN) |
Pass / Fail (PorF) |
Fault? |
Repaired on Site (YorN) |
DB2 |
4 |
Y |
P |
|
|
|
5 |
Y |
P |
|
|
|
6 |
Y |
P |
|
|
|
7 |
Y |
P |
|
|
|
8 |
Y |
P |
|
|
|
9 |
Y |
P |
|
|
|
10 |
Y |
P |
|
|
|
11 |
Y |
P |
|
|
|
12 |
Y |
P |
|
|
|
13 |
Y |
P |
|
|
|
14 |
Y |
P |
|
|
|
15 |
Y |
P |
|
|
|
16 |
Y |
P |
|
|
|
17 |
Y |
P |
|
|
|
18 |
Y |
P |
|
|
|
19 |
Y |
P |
|
|
|
20 |
Y |
P |
|
|
|
21 |
Y |
P |
|
|
|
23 |
Y |
P |
|
|
|
24 |
Y |
P |
|
|
Sub Board 3 |
1 |
Y |
P |
|
|
|
2 |
Y |
P |
|
|
|
4 |
Y |
P |
|
|
|
6 |
Y |
P |
|
|
|
7 |
Y |
P |
|
|
|
8 |
Y |
P |
|
|
|
9 |
Y |
P |
|
|
|
10 |
Y |
P |
|
|
|
11 |
Y |
P |
|
|
|
12 |
Y |
P |
|
|
|
13 |
Y |
P |
|
|
|
15 |
Y |
P |
|
|
|
19 |
Y |
P |
|
|
DB 1 |
1 |
Y |
P |
|
|
|
2 |
Y |
P |
|
|
|
3 |
Y |
P |
|
|
|
4 |
Y |
P |
|
|
|
5 |
Y |
P |
|
|
|
6 |
Y |
P |
|
|
|
7 |
Y |
P |
|
|
|
8 |
Y |
P |
|
|
|
9 |
Y |
P |
|
|
|
10 |
Y |
P |
|
|
|
11 |
Y |
P |
|
|
|
12 |
Y |
P |
|
|
|
13 |
Y |
P |
|
|
|
14 |
Y |
P |
|
|
|
15 |
Y |
P |
|
|
|
16 |
Y |
P |
|
|
|
17 |
Y |
P |
|
|
|
18 |
Y |
P |
|
|
|
19 |
Y |
P |
|
|
|
21 |
Y |
P |
|
|
|
22 |
Y |
P |
|
|
|
23 |
Y |
P |
|
|
|
25 |
Y |
P |
|
|
|
26 |
Y |
P |
|
|
|
27 |
Y |
P |
|
|
|
28 |
Y |
P |
|
|
|
29 |
Y |
P |
|
|
|
30 |
Y |
P |
|
|
|
31 |
Y |
P |
|
|
|
32 |
Y |
P |
|
|
|
33 |
Y |
P |
|
|
|
34 |
Y |
P |
|
|
|
35 |
Y |
P |
|
|
|
36 |
Y |
P |
|
|
|
42 |
Y |
P |
|
|
|
43 |
Y |
P |
|
|
|
44 |
Y |
P |
|
|
|
45 |
Y |
P |
|
|
|
46 |
Y |
P |
|
|
|
47 |
Y |
P |
|
|
|
---|
THERMOGRAPHIC TEST RESULTS |
THERMOGRAPHIC TEST RESULTS
|
---|
SF43 Exit/Emergency |
SF43 EXIT/EMERGENCY LIGHTING
|
---|
Exit/Emergency Light Checklist | - Check there has been no power interruption for at least 16 hours prior to test
- Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
- Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
- Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
|
---|
Exit/Emergency Light Checklist | - Check there has been no power interruption for at least 16 hours prior to test
- Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
- Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
- Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
- Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
|
---|
Timers | - Check timers for correct operation and timing
|
---|
Switched Socket Outlets | - Carry out visual check on SSOs for signs of misuse, blackening or deterioration
- Check and report any outlets with multiple power boards overloading
- Ensure any power boards used have an integral over-current limiter
|
---|
HTML Block |
|
---|
EMERGENCY LIGHTS | Distribution Board No. |
ID No. |
Surface mounted or recessed? (SorR) |
Lamp OK? (YorN) |
Battery OK? (YorN) |
Condition OK? (YorN) |
Pass / Fail (PorF) |
Fault |
Repaired on Site (YorN) |
Under Warranty (YorN) |
DB1 |
G6 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G7 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G8 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G9 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G10 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G11 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G12 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G13 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G14 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G15 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G14 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G16 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G15 |
S |
Y |
Y |
Y |
P |
|
|
|
|
G20 |
S (1x36w emergency batten) |
N |
N |
N |
F |
Failed 90 min test |
Y |
N |
|
G18 |
R |
Y |
Y |
Y |
P |
|
|
|
|
G20 (a) |
S (2x36w emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
G21 |
S (1x36w emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
G22 |
S (2x36w emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
G23 |
S (2x36w emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
G19 |
S 1x36w emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
L1-19 |
R |
Y |
Y |
Y |
P |
|
|
|
|
L1-21 |
R |
N |
N |
N |
F |
Failed to start |
Y |
Y |
|
L1-24(a) |
R |
Y |
Y |
Y |
P |
|
|
|
|
L1-24 |
R |
Y |
Y |
Y |
P |
|
|
|
|
L1-22 |
R |
Y |
Y |
Y |
P |
|
|
|
|
L1-20 |
R |
Y |
Y |
Y |
P |
|
|
|
Sub Board 3 |
L1-1 |
S (2x36w emergency batten) |
N |
N |
N |
F |
Failed 90 min test/ failed to start |
Y |
N |
|
3 |
R |
Y |
Y |
Y |
P |
|
|
|
|
2 |
R |
Y |
Y |
Y |
P |
|
|
|
|
1 |
R |
Y |
Y |
Y |
P |
|
|
|
|
18 |
R |
Y |
Y |
Y |
P |
|
|
|
|
5 |
S (4ft emergency batten) |
Y |
Y |
Y |
P |
|
|
|
|
---|
HTML Block |
|
---|
EXIT LIGHTS | Distribution Board No. |
ID No. |
Lamp OK? (YorN) |
Battery OK? (YorN) |
Condition OK? (YorN) |
Pass / Fail (PorF) |
Fault |
Repaired on Site (YorN) |
Under Warranty (YorN) |
DB1 |
7 |
Y |
Y |
Y |
P |
|
|
|
|
5 |
Y |
Y |
Y |
P |
|
|
|
|
6 |
Y |
Y |
Y |
P |
|
|
|
|
10 |
Y |
Y |
Y |
P |
|
|
|
|
8 |
Y |
Y |
Y |
P |
|
|
|
DB2 |
1 |
Y |
Y |
Y |
P |
|
|
|
|
2 |
Y |
Y |
Y |
P |
|
|
|
Sub Board 3 |
18 |
Y |
Y |
Y |
P |
|
|
|
|
5 |
Y |
Y |
Y |
P |
|
|
|
|
3 |
Y |
Y |
Y |
P |
|
|
|
|
4 |
Y |
Y |
Y |
P |
|
|
|
|
---|
SF44 General Lighting & Works |
SF44 GENERAL LIGHTING & WORKS
|
---|
General Checklist | - Check correct operation of all luminaries
- Report on any faulty luminaries/control gear
- Provide costing to repair/replace
|
---|
HTML Block |
|
---|
General Operation/Additional items | - Check with Store Manager to ensure there are no other issues
- Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
|
---|
HTML Block |
|
---|
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.au | Yes |
---|
Lighting Report | Description of all lighting installed in store (eg. 21w bare batten) |
Existing (YorN) |
1x36 bare battens |
Y |
2 x 36w bare and diffused battens |
Y |
1200mm LED Panel Light |
Y |
4ft LED Batten |
Y |
90mm LED downlights |
Y |
400w external flood lights |
Y |
|
---|
Are there any Warranty items needing to be repaired? | Yes |
---|
WARRANTY | Defect Item |
Location of Item (on premises) |
Quantity |
Details of fault/problem |
Manufacturer |
Part Number |
Repaired on Site |
Comments |
Recessed Emergency Light |
L1-21 |
1 |
Failed to start |
Clevertronics |
- |
Y |
|
|
---|
Geotag photo(s) | - Have you sent the Geotag photo(s) to maintenance@sturdie.com.au, referring to the Store Location in the email, e.g. Canberra City?
|
---|
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's | Defect Item |
Location of Item (on premises) |
Quantity |
Details of fault /problem |
Repaired on Site? (YorN) |
Quote to be sent? (YorN) |
To return to Site |
Comments |
Surface Mount Emergency Light |
G20 |
1 |
Failed 90 min test |
Y |
N |
N |
|
Emergency Batten |
L1-1 |
1 |
Failed 90 min test |
Y |
N |
N |
|
1200mm LED Troffer Light |
Level 1 Mezzanine |
1 |
Blown light |
Y |
N |
N |
Replaced with LED Panel. |
2x36w Troffer Light |
Level 1 managers office |
2 |
Blown lights |
Y |
N |
N |
Replaced with LED Panel. |
2x36w Troffer Light |
Level 1 men’s toilet |
1 |
Blown light |
Y |
N |
N |
Replaced with LED Panel. |
Light Boxes |
Ground floor throughout store |
9 |
Blown lights |
N |
TBA |
TBA |
Added to fortnightly repairs list. |
New power circuit needed |
Upstairs mezzanine level |
1 |
Circuits are overloaded and have just had a new LG Display installed and this is causing the circuit to overload |
N |
TBA |
TBA |
Added to fortnightly repairs list. |
|
---|
Site Status Selector | Store now fully compliant |
---|
Next Test Due in 6 months | 03/04/2024 |
---|
| |
---|
| |