StateACT
Date of Visit02/04/2024
Technician's NameWill Andrews
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number50F0015/0273
EmailEmail hidden; Javascript is required.
The Good Guys Site in ACTbelconnen

Location NameBelconnen
HTML Block
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

RCD Details (6 Month)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
Db1 1 Y P
Db1 2 Y P
Db1 3 Y P
Db1 4 Y P
Db1 5 Y P
Db1 6 Y P
Db1 7 Y P
Db1 8 Y P
Db1 9 Y P
Db1 10 Y P
Db1 11 Y P
Db1 12 Y P
Db1 13 Y P
Db1 14 Y P
Db1 15 Y P
Db1 16 Y P
Db1 17 Y P
Db1 18 Y P
Db1 19 Y P
Db1 21 Y P
Db1 22 Y P
Db1 23 Y P
Db1 25 Y P
Db1 26 Y P
Db1 27 Y P
Db1 28 Y P
Db1 29 Y P
Db1 30 Y P
Db1 31 Y P
Db1 32 Y P
Db1 33 Y P
Db1 34 Y P
Db1 35 Y P
Db1 36 Y P
Db1 42 Y P
Db1 43 Y P
Db1 44 Y P
Db1 45 Y P
Db1 46 Y P
Db1 47 Y P
Db2 4 Y P
Db2 5 Y P
Db2 6 Y P
Db2 7 Y P
Db2 8 Y P
Db2 9 Y P
Db2 10 Y P
Db2 11 Y P
Db2 12 Y P
Db2 13 Y P
Db2 14 Y P
Db2 15 Y P
Db2 16 Y P
Db2 17 Y P
Db2 18 Y P
Db2 19 Y P
Db2 20 Y P
Db2 21 Y P
Db2 23 Y P
Db2 24 Y P
Db3 1 Y P
Db3 2 Y P
Db3 4 Y P
Db3 6 Y P
Db3 7 Y P
Db3 8 Y P
Db3 9 Y P
Db3 10 Y P
Db3 11 Y P
Db3 12 Y P
Db3 13 Y P
Db3 15 Y P
Db3 19 Y P
SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install label with date & fitting number
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
Db2 L1-20 R Y Y Y P
Db2 L1-22 R Y Y Y P
Db2 L1-24 R Y Y Y P
Db2 L1- R Y Y Y P
Db2 L1-21 R Y Y Y P
Db2 L1-19 R Y Y Y P
Db2 L1-15 R Y Y Y P
Db1 13 S Y Y Y P
Db1 14 S Y Y Y P
Db1 15 S Y Y Y P
Db1 16 S Y Y Y P
Db1 6 S Y Y Y P
Db1 7 S Y Y Y P
Db1 8 S Y Y Y P
Db1 9 S Y Y Y P
Db1 10 S Y Y Y P
Db1 11 S N N N F Failed 90 min test Y N
Db1 12 S Y Y Y P
Db1 20 S Y Y Y P
Db1 21 Fluro 1 x36w Y Y Y P
Db1 22 Fluro 2 x 36w Y Y Y P
Db1 23 Fluro 2 x 36w Y Y Y P
Db1 19 Fluro 1 x 36w Y Y Y P
Db3 5 4ft LED Batten Emergency Y Y Y P
Db3 18 R Y Y Y P
Db3 12 R Y Y Y P
Db3 3 R Y Y Y P
Db3 L1- 4ft Emergency Batten Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
Db2 1 Y Y Y P
Db2 2 Y Y Y P
Db3 3 Y Y Y P
Db3 18 Y Y Y P
Db3 4 Y Y Y P
Db3 5 Y Y Y P
Db1 6 Y Y Y P
Db1 5 Y Y Y P
Db1 7 Y Y Y P
Db1 8 Y Y Y P
Db1 10 Y Y Y P
Db1 9 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
1 x 36w bare battens Y
2 x 36w bare and diffused battens Y
1200mm LED Troffer Light Y
2 x 28w troffers Y
90mm LED downlights Y
400w external flood lights Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
1200mm LED Troffer Light Upstairs Mezzanine level near switchboard cupboard 1 Blown light Y N N Replaced with LED panel
Surface Mount Emergency Light #11 Downstairs (Near Laptops) 1 Failed 90min test Y N N
Light boxes Throughout store 7 Blown lights and is tripping the circuit Y N N Replaced blown lights in 7 light boxes with new 12w LED linkable lights (5 per light box, total of 35). Also required 7 x power leads and plug bases
Site Status SelectorStore now fully compliant
Next Test Due in 6 months02/10/2024