Partner NameBuilt Services
StateSA
Date of Visit23/09/2024
Technician's NameGlenn Rowe
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number50F0021/0066
EmailEmail hidden; Javascript is required.
The Good Guys Site in SAnoarlunga

Location NameNoarlunga
HTML Block
Test PeriodBiennial Test (once every two years)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Biennial)
Distribution Board No. Circuit No. Push Button (YorN) 0 Degrees 180 Degrees Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB SHOP 5 Y 029 040 P
7 Y 032 043 P
9 Y 029 040 P
10 Y 029 040 P
11 Y 029 040 P
12 Y 029 040 P
13 Y 029 040 P
14 Y 031 043 P
15 Y 039 027 P
16 Y 023 033 P
17 Y 032 043 P
18 Y 032 042 P
19 Y 033 100 P
21 Y 032 043 P
22 Y 034 043 P
23 Y 029 040 P
24 Y 032 042 P
25 Y 032 043 P
26 Y 027 022 P
27 Y 029 021 P
28 Y 028 039 P
29 Y 030 041 P
30 Y 028 033 P
31 Y 023 033 P
32 Y 071 085 P
33 Y 029 031 P
35 Y 026 037 P
36 Y 024 019 P
37 Y 028 033 P
38 Y 023 100 P
39 Y 029 033 P
40 Y 040 034 P
41 Y 030 037 P
42 Y 029 040 P
43 Y 029 040 P
44 Y 024 032 P
47 Y 024 033 P
48 Y 029 040 P
49 Y 028 033 P
50 Y 023 032 P
52 Y 029 042 P
54 Y 029 040 P
56 Y 029 021 P
60 Y 029 040 P
62 Y 033 043 P
64 Y 028 033 P
66 Y 028 033 P
68 Y 024 039 P
70 Y 028 033 P
MSB R3,4,5 W2,3,4 B3,4,16 Y 209 145 P
Y 164 186 P
Y 228 240 P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
  • Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
MSB A1 1 R Y Y Y P
2 S Y Y Y P
3 S Y Y Y P
4 R Y Y Y P
5 R Y Y Y P
6 R Y Y Y P
11 R Y Y Y P
12 S Y Y Y P
13 R Y Y Y P
14 R Y Y Y P
15 R Y Y Y P
16 R Y Y Y P
17 R Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
MSB A1 7 Y Y Y P
8 Y Y Y P
9 Y Y Y P
10 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
LED Strip Light Fridges and Printers 1 Not operational Y N N
Site Status SelectorStore now fully compliant
Next Test Due in 6 months24/03/2025