Partner NameCommlec Electrical PTY LTD
StateNSW
Date of Visit24/03/2025
Technician's NameMitch Cutts
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number50F0015/0535
EmailEmail hidden; Javascript is required.
The Good Guys Site in NSWerina

Location NameErina
HTML Block
Test Period6 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

RCD Details (6 Month)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
DB1 1 Y P
DB1 3 Y P
DB1 5 Y P
DB1 7 Y P
DB1 8 Y P
DB1 9 Y P
DB1 10 Y P
DB1 11 Y P
DB1 12 Y P
DB1 13 Y P
DB1 14 Y P
DB1 15 Y P
DB1 16 Y P
DB1 17 Y P
DB1 18 Y P
DB1 19 Y P
DB1 20 Y P
DB1 21 Y P
DB1 22 Y P
DB1 23 Y P
DB1 24 Y P
DB1 25 Y P
DB1 26 Y P
DB1 27 Y P
DB1 28 Y P
DB1 29 Y P
DB1 30 Y P
DB1 31 Y P
DB1 32 Y P
DB1 33 Y P
DB1 34 Y P
DB1 35 Y P
DB1 36 Y P
DB1 37 Y P
DB1 38 Y P
DB1 39 Y P
DB1 40 Y P
DB1 41 Y P
DB1 42 Y P
DB1 43 Y P
DB1 44 Y P
DB1 46 Y P
DB2 2 Y P
DB2 4 Y P
DB2 6 Y P
DB2 8 Y P
DB2 10 Y P
DB2 12 Y P
DB2 14 Y P
DB2 16 Y P
DB2 18 Y P
SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB1 4 S Y Y Y P
DB1 5 S Y Y Y P
DB1 6 S Y Y Y P
DB1 7 S Y Y Y P
DB1 8 S Y Y Y P
DB1 9 S Y Y Y P
DB1 8 S Y Y Y P
DB1 11 S Y Y Y P
DB1 10 S Y Y Y P
DB1 13 S Y Y Y P
DB1 14 S Y Y Y P
DB1 17 R Y Y Y P
DB1 18 R Y Y Y P
DB1 19 R Y Y Y P
DB1 20 R Y Y Y P
DB1 21 R Y Y Y P
DB1 22 R Y Y Y P
DB1 23 R Y Y Y P
DB1 25 S Y Y Y P
DB1 24 S Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB1 1 Y Y Y P
DB1 2 Y Y Y P
DB1 3 Y Y Y P
DB1 4 Y Y Y P
DB1 5 Y Y Y P
DB1 6 Y Y Y P
DB1 16 Y Y Y P
DB1 17 Y Y Y P
DB1 18 Y Y Y P
DB1 19 Y Y Y P
DB1 20 Y Y Y P
DB1 21 Y Y Y P
DB1 22 Y Y Y P
DB1 23 Y Y Y P
DB1 26 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
150W LED HI BAYS Y
35W LED Surface Mount Batten Lights Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
EMERGENCY AND EXITS WAREHOUSE 3 NO.24,25,29 NOT CONNECTED TO TEST STATION N N N Added to the fortnightly repairs list
Site Status SelectorCompleted but with repairs required
Next Test Due in 6 months24/09/2025