Carry out push button test and record the results below.
THERMOGRAPHIC TEST RESULTS
THERMOGRAPHIC TEST RESULTS
RCD Details (6 Month)
Distribution Board No.
Circuit No.
Push Button (YorN)
Pass / Fail (PorF)
Fault?
Repaired on Site (YorN)
DB 01
R1
Y
P
DB 01
W1
Y
P
DB 01
B1
Y
P
DB 01
R2
Y
P
DB 01
W2
Y
P
DB 01
B2
Y
P
DB 01
R3
Y
P
DB 01
W3
Y
P
DB 01
B3
Y
P
DB 01
R4
Y
P
DB 01
W4
Y
P
DB 01
B4
Y
P
DB 01
R5
Y
P
DB 01
W5
Y
P
DB 01
B5
Y
P
DB 01
R6
Y
P
DB 01
W6
Y
P
DB 01
B6
Y
P
DB 01
R7
Y
P
DB 01
R8
Y
P
DB 01
W8
Y
P
DB 01
B8
Y
P
DB 01
W9
Y
P
DB 01
R10
Y
P
DB 01
W10
Y
P
DB 01
B10
Y
P
DB 01
R11
Y
P
DB 01
W11
Y
P
DB 01
B11
Y
P
DB 01
R12
Y
P
DB 01
W12
Y
P
DB 01
B12
Y
P
DB 01
R13
Y
P
DB 01
W13
Y
P
DB 01
B13
Y
P
DB 01
R14
Y
P
DB 01
W14
Y
P
DB 01
B14
Y
P
DB 01
R15
Y
P
DB 01
W15
Y
P
DB 01
B15
Y
P
DB 01
R16
Y
P
DB 01
W16
Y
P
DB 01
B16
Y
P
DB 01
R17
Y
P
DB 01
W17
Y
P
DB 01
B17
Y
P
DB 01
R18
Y
P
DB 01
W18
Y
P
DB 01
B18
Y
P
DB 01
B19
Y
P
DB 01
R20
Y
P
DB 01
RWB21, RW23
Y
P
DB 01
B23
Y
P
DB 01
R26
Y
P
DB 01
W26
Y
P
DB 01
B26
Y
P
DB 01
R28
Y
P
DB 01
W28
Y
P
DB 01
B28
Y
P
DB 01
R33
Y
P
DB 01
W33
Y
P
DB 01
B33
Y
P
DB 01
R34
Y
P
DB 01
W34
Y
P
DB 01
B34
Y
P
DB 01
R35
Y
P
DB 01
W35
Y
P
DB 01
B35
Y
P
DB 01
R36
Y
P
DB 01
W36
Y
P
DB 01
B36
Y
P
DB 01
R37
Y
P
DB 01
W37
Y
P
DB 01
B37
Y
P
DB 01
R45
Y
P
DB 01
W45
Y
P
DB 01
B45
Y
P
DB 01
R46
Y
P
DB 01
W46
Y
P
DB 01
B46
Y
P
DB 01
R47
Y
P
DB 01
W47
Y
P
DB 01
B47
Y
P
DB 01
R48
Y
P
DB 01
W48
Y
P
DB 01
B48
Y
P
DB 01
R49
Y
P
DB 01
W49
Y
P
DB 01
B49
Y
P
DB 01
R50
Y
P
DB 01
W50
Y
P
DB 01
B50
Y
P
DB 01
R46
Y
P
DB 01
W46
Y
P
DB 01
B46
Y
P
DB 01
R48
Y
P
DB 01
W48
Y
P
DB 01
B48
Y
P
DB 02
CB01
Y
P
DB 02
CB02
Y
P
DB 02
CB03
Y
P
DB 02
CB04
Y
P
DB 02
CB05
Y
P
DB 02
CB06
Y
P
DB 02
CB08
Y
P
DB 02
CB09
Y
P
DB 02
CB10
Y
P
DB 02
CB11
Y
P
DB 02
CB12
Y
P
DB 02
CB13
Y
P
DB 02
CB14
Y
P
DB 02
CB15
Y
P
DB 02
CB16
Y
P
DB 02
CB17
Y
P
DB 02
CB18
Y
P
DB 02
CB19
Y
P
DB 02
CB21
Y
P
DB 02
CB22
Y
P
DB 02
CB23
Y
P
DB 02
CB25
Y
P
DB 02
CB26
Y
P
DB 02
CB27
Y
P
DB 02
CB28
Y
P
DB 02
CB29
Y
P
DB 02
CB30
Y
P
DB 02
CB31
Y
P
DB 02
CB33
Y
P
DB 02
CB35
Y
P
SF43 Exit/Emergency
SF43 EXIT/EMERGENCY LIGHTING
Timers
Check timers for correct operation and timing
Switched Socket Outlets
Carry out visual check on SSOs for signs of misuse, blackening or deterioration
Check and report any outlets with multiple power boards overloading
Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No.
ID No.
Surface mounted or recessed? (SorR)
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
DB 01
3
S
Y
Y
Y
P
7
S
Y
Y
Y
P
9
S
Y
Y
Y
P
11
S
Y
Y
Y
P
14
S
Y
Y
Y
P
16
S
Y
Y
Y
P
18
S
Y
Y
Y
P
20
S
Y
Y
Y
P
25
S
Y
Y
Y
P
27
S
Y
Y
Y
P
30
S
Y
Y
Y
P
32
R
Y
Y
Y
P
34
R
Y
Y
Y
P
36
S
Y
Y
Y
P
40
S
Y
Y
Y
P
44
S
Y
Y
Y
P
45
S
N
N
N
F
Failed 90 minute test
Y
N
46
S
Y
Y
Y
P
50
R
Y
Y
Y
P
51
R
Y
Y
Y
P
53
R
Y
Y
Y
P
54
R
Y
Y
Y
P
55
R
Y
Y
Y
P
56
R
Y
Y
Y
P
57
R
Y
Y
Y
P
58
R
Y
Y
Y
P
59
S
Y
Y
Y
P
60
S
Y
Y
Y
P
61
S
Y
Y
Y
P
62
S
Y
Y
Y
P
63
S
Y
Y
Y
P
64
S
Y
Y
Y
P
65
S
Y
Y
Y
P
66
S
Y
Y
Y
P
HTML Block
EXIT LIGHTS
Distribution Board No.
ID No.
Lamp OK? (YorN)
Battery OK? (YorN)
Condition OK? (YorN)
Pass / Fail (PorF)
Fault
Repaired on Site (YorN)
Under Warranty (YorN)
DB 01
1
Y
Y
Y
P
2
Y
Y
Y
P
4
Y
Y
Y
P
5
Y
Y
Y
P
6
Y
Y
Y
P
7
Y
Y
Y
P
10
Y
Y
Y
P
12
Y
Y
Y
P
13
Y
Y
Y
P
15
Y
Y
Y
P
17
Y
Y
Y
P
19
Y
Y
Y
P
21
Y
Y
Y
P
23
Y
Y
Y
P
24
Y
Y
Y
P
26
Y
Y
Y
P
28
Y
Y
Y
P
29
Y
Y
Y
P
31
Y
Y
Y
P
33
Y
Y
Y
P
35
Y
Y
Y
P
37
Y
Y
Y
P
39
Y
Y
Y
P
41
Y
Y
Y
P
42
Y
Y
Y
P
43
Y
Y
Y
P
47
Y
Y
Y
P
48
Y
Y
Y
P
49
Y
Y
Y
P
52
Y
Y
Y
P
SF44 General Lighting & Works
SF44 GENERAL LIGHTING & WORKS
General Checklist
Check correct operation of all luminaries
Report on any faulty luminaries/control gear
Provide costing to repair/replace
HTML Block
General Operation/Additional items
Check with Store Manager to ensure there are no other issues
Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.au
Yes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten)
Existing (YorN)
400w Hibay
Y
400w Lowbay
Y
400w Lowbay Defused
Y
LED Downlight SAL
Y
Jumbo Exit
Y
2 by PAR 38 Spot
Y
LED Oyster Light
Y
150w Round MH Shoplight
Y
Exits
Y
Recessed Emergency Spitfire
Y
Surface Mount Emergency Spitfire
Y
40w LED Batten - DAVIS
Y
Are there any Warranty items needing to be repaired?
No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item
Location of Item (on premises)
Quantity
Details of fault /problem
Repaired on Site? (YorN)
Quote to be sent? (YorN)
To return to Site
Comments
Hibay
1x Coffee, 1x Samsung Fridges, 3x BOH
5
Not Illuminated
Y
N
N
Scissor Lift was Required
LG Washers and Samsung Washers CB18
Front of Store Washers
2
2 x Displays need to have their circuits split
Y
N
N
Scissor Lift was required to split LG & Samsung Washing Machine Displays. CB18 was split allowing LG to remain on CB18 and a new RCD was installed to power Samsung Washers Display
Surface Mount Emergency Light #45
BOH
1
Failed 90 minute test
Y
N
N
Scissor Lift was Required
Site Status Selector
Store now fully compliant
Next Test Due in 6 months
10/11/2025