StateVIC
Date of Visit11/08/2025
Technician's NameMatt Setches
Which Company are you working for?Sturdie Trade Services
Sturdie Job Number50f0680/0003
EmailEmail hidden; Javascript is required.
The Good Guys Site in VICmaribyrnong_warehouse

Location Namemaribyrnong_warehouse
HTML Block
Test Period12 Monthly (90 minutes)
Push Button Test
  • Carry out push button test for correct operation
Carry out push button test for correct operation
HTML Block
Carry out test with RCD Tester

Carry out push button test and record the results below.

RCD Details (Initial/12 Months)
Distribution Board No. Circuit No. Push Button (YorN) Pass / Fail (PorF) Fault? Repaired on Site (YorN)
Unit 3 sub board 7 Y P
11 Y P
THERMOGRAPHIC TEST RESULTS

THERMOGRAPHIC TEST RESULTS

SF43 Exit/Emergency

SF43 EXIT/EMERGENCY LIGHTING

Exit/Emergency Light Checklist
  • Check there has been no power interruption for at least 16 hours prior to test
  • Carry out discharge test to ensure the luminaries remain illuminated for the required in service duration (90 minutes)
  • Re-instate power to luminaries and check that the battery charge operation indicator functions correctly
  • Report any failures and replace faulty fittings with stock provided by Sturdie Trade Services – install sticker with date & fitting number
  • Using a clean cloth, clean reflective surfaces of all exit and emergency luminaires.
Timers
  • Check timers for correct operation and timing
Switched Socket Outlets
  • Carry out visual check on SSOs for signs of misuse, blackening or deterioration
  • Check and report any outlets with multiple power boards overloading
  • Ensure any power boards used have an integral over-current limiter
HTML Block
EMERGENCY LIGHTS
Distribution Board No. ID No. Surface mounted or recessed? (SorR) Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-4 5 S Y Y Y P
DB-4 6 S Y Y Y P
DB-4 7 S Y Y Y P
DB-4 8 R Y Y Y P
DB-4 9 R Y Y Y P
DB-4 10 R Y Y Y P
DB-3 11 S Y Y Y P
DB-3 12 S Y Y Y P
DB-3 13 S Y Y Y P
DB-3 14 S Y Y Y P
DB-4 15 R Y Y Y P
DB-4 16 R Y Y Y P
18 R Y Y Y P
HTML Block
EXIT LIGHTS
Distribution Board No. ID No. Lamp OK? (YorN) Battery OK? (YorN) Condition OK? (YorN) Pass / Fail (PorF) Fault Repaired on Site (YorN) Under Warranty (YorN)
DB-4 1 Y Y Y P
2 Y Y Y P
3 Y Y Y P
DB-4 4 Y Y Y P
DB-4 17 Y Y Y P
SF44 General Lighting & Works

SF44 GENERAL LIGHTING & WORKS

General Checklist
  • Check correct operation of all luminaries
  • Report on any faulty luminaries/control gear
  • Provide costing to repair/replace
HTML Block
General Operation/Additional items
  • Check with Store Manager to ensure there are no other issues
  • Ensure any other electrical work is completed as per Sturdie Trade Services ie, affix label to switchboard
HTML Block
Are there accurate switchboard legends within each switchboard? Please take a photo of legend/s & send with report to maintenance@sturdie.com.auYes
Lighting Report
Description of all lighting installed in store (eg. 21w bare batten) Existing (YorN)
LED Hi-bay lights Y
36W diffused lights Y
Are there any Warranty items needing to be repaired?No
LIST OF REPAIRS & ADDITIONAL WORKS REQUIRED - (ALL FIELDS MANDATORY) - Please supply photo's
Defect Item Location of Item (on premises) Quantity Details of fault /problem Repaired on Site? (YorN) Quote to be sent? (YorN) To return to Site Comments
Hi-bay Warehouse 1 Failed to luminate N Y Y Require 1x hi-bay to replace faulty. Scissor lift Required to reach 7m
Next Test Due in 6 months11/02/2026